Multiple Choice
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) the project manager cannot force subcontractors to use this project management approach.
B) the feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) subcontractors routinely operate according to calendar delivery dates.
D) the corporate culture of "no blame" does not naturally extend to subcontractors.
Correct Answer:

Verified
Correct Answer:
Verified
Q57: Use these activity durations (that have been
Q58: In order to estimate completion of a
Q59: A resource constraint can be exploited using
Q60: According to CCPM:<br>A)using a point estimate for
Q61: The student syndrome of wasting extra safety
Q63: Why aren't both negative and positive project
Q64: A project consists of three activities with
Q65: CCPM advocates modification of the project schedule
Q66: In applying the principle of common cause
Q67: A project consists of four consecutive tasks