Multiple Choice
In applying the principle of common cause variation to the theory of CCPM,it is important to:
A) not make adjustments to projects when the variation in project performance lies within the range of common-cause variance.
B) immediately call meetings for all key stakeholders if common cause variation is detected.
C) include special cause variation in project risk simulation since there is a chance it may occur.
D) perform risk management on aggregated project risks.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: The term capacity constraint buffer refers to
Q50: Your next project consists of 8 consecutive
Q61: The student syndrome of wasting extra safety
Q62: Subcontractor deliveries are difficult to schedule with
Q63: Why aren't both negative and positive project
Q64: A project consists of three activities with
Q65: CCPM advocates modification of the project schedule
Q67: A project consists of four consecutive tasks
Q68: A project consists of three activities with
Q71: Successful implementation of CCPM depends on first:<br>A)identifying