Multiple Choice
Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers. The critical chain does NOT pass through:
A) Activity A.
B) Activity F.
C) Activity E.
D) Activity D.
Correct Answer:

Verified
Correct Answer:
Verified