Multiple Choice
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology?
A) 48
B) 32
C) 64
D) 43.5
Correct Answer:

Verified
Correct Answer:
Verified
Q16: If a project activity experiences negative variation:<br>A)the
Q27: In classic project management,activity durations are estimated
Q28: Create and solve an example of at
Q60: Use the project information in the table
Q67: A project consists of three activities with
Q75: Which statement about critical chain project management
Q86: List any three criticisms of critical chain
Q88: What is the difference between common cause
Q92: In order to estimate completion of a
Q93: All five members of a project team