Which of the Following Items Best Describe the Process Steps

Question 15

Multiple Choice

Which of the following items best describe the process steps to construct a Work Breakdown Structure (WBS) ?


A) identify major deliverables - divide into smaller deliverables - continue until right size - review
B) identify smallest deliverables - assemble into larger deliverables - continue until right size - review
C) identify project goals - decompose into objectives - develop metrics - document results
D) identify WBS components - identify WBS elements - identify work packages - develop WBS dictionary

Correct Answer: