A Typical Change Request Form Will Include Which of the Following

Question 16

Multiple Choice

A typical change request form will include which of the following content items?


A) a description of the change along with the impact of making the change
B) a status accounting summary of previous changes
C) a change register relating the current change to others proposed
D) a change control process flow diagram

Correct Answer: