Multiple Choice
Formally documented procedures that define how project deliverables and documentation will be controlled,changed and approved are collectively known by which of the following terms?
A) scope creep
B) a change control system
C) a configuration management plan
D) a scope management plan
Correct Answer:

Verified
Correct Answer:
Verified