Multiple Choice
All of the following conventions are widely adopted when project teams create the second level of the project Work Breakdown Structure (WBS) EXCEPT:
A) The second level may be organized by project phase.
B) The second level may be organized by major design components.
C) The second level may be organized by work function.
D) The second level may be organized by activities and tasks