Multiple Choice
Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?
A) staggered project start dates
B) resource buffers
C) checklists, templates, WBS
D) staggered project end dates
Correct Answer:

Verified
Correct Answer:
Verified