Multiple Choice
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3.Based on the information provided,what is the expected duration of this project?
A) 15 days
B) 16 days
C) 17 days
D) 30 days
Correct Answer:

Verified
Correct Answer:
Verified