Multiple Choice
Which of the following statements correctly describes the critical path?
A) It is the shortest sequence of activities through the project network.
B) It determines the latest possible end date of the project.
C) It consists only of activities with zero float (slack) .
D) It consists only of activities with lag times
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A successor activity follows a predecessor activity
Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-5 Duration
Q14: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q17: There is often terrific pressure to complete
Q18: GANTT refers to the Generalized Activity Network
Q21: In order for activities to be useful
Q22: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q29: The total amount of time a schedule
Q40: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-6 Network
Q52: Estimating the number of work periods that