Figure 7-5 Duration Estimates

Question 13

Multiple Choice

  Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D -  Package Item ?​  A)  9 days  B)  9.5 days  C)  10 days  D)  12 days Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?​ 


A)  9 days 
B)  9.5 days 
C)  10 days 
D)  12 days