Multiple Choice
Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?
A) 9 days
B) 9.5 days
C) 10 days
D) 12 days
Correct Answer:

Verified
Correct Answer:
Verified
Q8: A Gantt chart is a horizontal bar
Q9: The amount of time a schedule activity
Q10: A mandatory dependency is a logical relationship
Q11: The schedule activity that determines when the
Q12: The sequencing of activities is often based
Q14: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-2 Research
Q15: Which of the following statements correctly describes
Q16: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-3 System
Q17: There is often terrific pressure to complete
Q18: GANTT refers to the Generalized Activity Network