Multiple Choice
Figure 8-1 RACI Chart
-Consider the RACI chart presented in Figure 8-1 (RACI stands for Responsible,Approve,Consult,Inform) .Who is responsible for development of the specification?
A) the project manager
B) the project engineer
C) the contract officer
D) the data manager
Correct Answer:

Verified
Correct Answer:
Verified