Figure 8-3 Programmers Resource Histogram

Question 7

Multiple Choice

  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.Which activity is an ideal candidate to delay in order to achieve a feasible schedule?  A)  Activity A - Define Requirements  B)  Activity B - Design Application  C)  Activity C - Draft User Manual  D)  Activity F - Correct Defects Figure 8-3 Programmers Resource Histogram
-Consider the programmers resource histogram presented in Figure 8-3.Which activity is an ideal candidate to delay in order to achieve a feasible schedule? 


A)  Activity A - Define Requirements 
B)  Activity B - Design Application 
C)  Activity C - Draft User Manual 
D)  Activity F - Correct Defects