Multiple Choice
The project manager is responsible for selecting appropriate quality standards for the project.Typically,these standards apply to all of the following EXCEPT:
A) team selection criteria
B) documentation created during the project
C) deliverables created by the project
D) materials and related inputs used by the project
Correct Answer:

Verified