Multiple Choice
After completing detailed planning for a project,it is often helpful for the project manager and team to apply a sanity test to the project plan.Which of the following accurately describes the application of a sanity test?
A) It is based largely on the expectations of supervisors and sponsors.
B) It is primarily focused on the team members.
C) It should include questions to ensure budgets, schedules and resource plans are reasonable and achievable.
D) It focuses on whether the project charter should be changed
Correct Answer:

Verified
Correct Answer:
Verified
Q12: The quality revolution introduced many tools that
Q13: Manage Quality is the process of using
Q14: During which DMAIC phase would you find
Q15: The International Organization for Standardization (ISO) developed a
Q16: As part of the Control Quality process there
Q18: The goal of empowered performance is to
Q19: Stakeholder satisfaction consists of identifying all stakeholders
Q20: Which of the following serves as a
Q21: The purpose of process control is to
Q22: Which of the following activities are typically