menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    An Activity with Two or More Immediate Predecessors Is A(n)
Solved

An Activity with Two or More Immediate Predecessors Is A(n)

Question 3

Question 3

Multiple Choice

An activity with two or more immediate predecessors is a(n) :


A) merge activity.
B) burst activity.
C) float activity.
D) event.

Correct Answer:

verifed

Verified

Related Questions

Q1: What is the early start time for

Q2: A gentleman farmer maniacally works on academic

Q5: Use the information in the table to

Q6: A project has the precedence requirements and

Q7: What is the slack time for activity

Q8: Activity Z has estimates a = 5,b

Q9: What is the early start time for

Q10: The amount of time that an activity

Q80: Preceding activities are those that must occur

Q81: In assigning a value for the most

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines