    In Assigning a Value for the Most Pessimistic (B)duration,the Project
Solved

In Assigning a Value for the Most Pessimistic (B)duration,the Project

Question 81

Question 81

True/False

In assigning a value for the most pessimistic (b)duration,the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q76: What is the early start time

Q77: A project has the precedence requirements

Q78: What is the early finish time

Q79: A gentleman farmer maniacally works on

Q80: Preceding activities are those that must occur

Q82: An activity has an expected duration and

Q83: What is the late finish time

Q84: Consider a project composed of activities X

Q85: Hammock activities break a task into greater

Q86: The least amount of float is found:<br>A)In

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines