Multiple Choice
Network logic suggests that:
A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A,B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q12: Float is always measured in exactly the
Q26: Burst activities are those with two or
Q33: What is the late start time for
Q34: Phoebe B.Beebee is constructing a canal for
Q35: What is the earliest that Activity D
Q36: A gentleman farmer maniacally works on academic
Q39: _ activities can be used as summaries
Q41: Activities that can be worked on simultaneously
Q42: The late finish times are determined by
Q93: Negative float exists when a project's critical