    What Is the Earliest That Activity D Can Begin If
Solved

What Is the Earliest That Activity D Can Begin If

Question 35

Question 35

Multiple Choice

What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days? What is the earliest that Activity D can begin if Activity A takes 3 days,Activity B takes 5 days,and Activity C takes 7 days?   A) day 15 B) day 7 C) day 5 D) day 3


A) day 15
B) day 7
C) day 5
D) day 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: A merge activity has two or more

Q12: Float is always measured in exactly the

Q26: Burst activities are those with two or

Q30: Use the information in the table to

Q33: What is the late start time for

Q34: Phoebe B.Beebee is constructing a canal for

Q36: A gentleman farmer maniacally works on academic

Q37: Network logic suggests that: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2943/.jpg" alt="Network

Q39: _ activities can be used as summaries

Q93: Negative float exists when a project's critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines