Multiple Choice
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
A) optimistic duration.
B) pessimistic duration.
C) most likely duration.
D) normal duration.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: The PERT technique assumes that durations are
Q37: What is laddering and what advantages can
Q86: Project Test Bank is composed of activities
Q87: Use the network diagram and activity lengths
Q87: Laddering is a technique that allows the
Q88: A(n)_ is a project schedule whose start
Q90: A gentleman farmer maniacally works on academic
Q91: Prior to creating a network,it is important
Q92: Use the information in the table to
Q94: Concurrent activities are:<br>A)activities that must be done