Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the standard deviation of the project's critical path?
A) 1.33 days
B) 1.56 days
C) 1.25 days
D) 1.75 days
Correct Answer:

Verified
Correct Answer:
Verified
Q10: The PERT technique assumes that durations are
Q37: What is laddering and what advantages can
Q86: Project Test Bank is composed of activities
Q87: Use the network diagram and activity lengths
Q88: A(n)_ is a project schedule whose start
Q89: The length of time expected to complete
Q91: Prior to creating a network,it is important
Q92: Use the information in the table to
Q94: Concurrent activities are:<br>A)activities that must be done
Q95: Thanks to excessive dilly dallying,the subcontractor grossly