Question 28

Question 28

Multiple Choice

Use the information in the table to determine the slack time for Activity B. Use the information in the table to determine the slack time for Activity B.   A) 6 days B) 4 days C) 2 days D) 0 days


A) 6 days
B) 4 days
C) 2 days
D) 0 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: A merge activity has two or more

Q23: Which technique would accelerate the completion of

Q24: You must know the mean of an

Q25: A gentleman farmer maniacally works on academic

Q26: A sequence of activities defined by the

Q29: Use the values in the table to

Q30: Use the information in the table to

Q32: What does a network diagram illustrate and

Q33: What is the late start time for

Q93: Negative float exists when a project's critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines