Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?
A) 32 days
B) 33 days
C) 34 days
D) 35 days
Correct Answer:

Verified
Correct Answer:
Verified
Q21: One of the defining points of a
Q22: An activity has an optimistic time estimate
Q23: Which technique would accelerate the completion of
Q24: You must know the mean of an
Q26: A sequence of activities defined by the
Q28: Use the information in the table to
Q29: Use the values in the table to
Q30: Use the information in the table to
Q32: What does a network diagram illustrate and
Q48: Activity float is the difference between the