Multiple Choice
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?
A) 3
B) 5
C) 7
D) 9
Correct Answer:

Verified
Correct Answer:
Verified
Q7: What is the slack time for activity
Q8: Activity Z has estimates a = 5,b
Q9: What is the early start time for
Q10: The amount of time that an activity
Q13: Ray's shipment of materials hit every red
Q14: The term ordered activity means:<br>A)tasks must either
Q15: Use the network diagram and activity lengths
Q16: Based on the activity network pictured,what is
Q17: _ activities have two or more immediate
Q80: Preceding activities are those that must occur