Solved

A Project Has the Precedence Requirements and Activity Durations Shown

Question 110

Multiple Choice

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project? A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project?   A) combine activities A,B,C B) combine activities B,E,H C) combine activities E,F D) combine activities G,H,I


A) combine activities A,B,C
B) combine activities B,E,H
C) combine activities E,F
D) combine activities G,H,I

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions