Multiple Choice
A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides to represent a few activities by a hammock activity.Which is a legitimate hammock activity for this project?
A) combine activities A,B,C
B) combine activities B,E,H
C) combine activities E,F
D) combine activities G,H,I
Correct Answer:

Verified
Correct Answer:
Verified