Multiple Choice
A project's duration can be reduced by:
A) shortening the duration of critical path tasks.
B) adding tasks to the critical path.
C) adding shorter routes around the critical path.
D) completing the backward pass first.
Correct Answer:

Verified
Correct Answer:
Verified