Multiple Choice
A key for developing project cost estimates is to:
A) cost the project while considering the total package.
B) cost the project on a work package and task basis.
C) cost the project on a major module basis.
D) cost the project and add 33% for contingency.
Correct Answer:

Verified
Correct Answer:
Verified