Solved

The Order of Magnitude Cost Estimate Is Used When

Question 72

Multiple Choice

The order of magnitude cost estimate is used when:


A) ballpark estimates are not considered accurate enough.
B) historical data are readily available.
C) information or time is scarce.
D) parametric estimation has already been performed.

Correct Answer: