Multiple Choice
The order of magnitude cost estimate is used when:
A) ballpark estimates are not considered accurate enough.
B) historical data are readily available.
C) information or time is scarce.
D) parametric estimation has already been performed.
Correct Answer:

Verified
Correct Answer:
Verified