menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 13: Project Evaluation and Control
  5. Question
    The Earned Value Divided by the Actual,cumulative Cost of the Work
Solved

The Earned Value Divided by the Actual,cumulative Cost of the Work

Question 113

Question 113

Multiple Choice

The earned value divided by the actual,cumulative cost of the work to date is the:


A) cost performance index.
B) budgeted cost at completion index.
C) budget efficiency index.
D) schedule performance index.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q95: Earned value directly links all three primary

Q107: A(n)_ identifies the stage of completion each

Q108: If significant deviations from the project plan

Q109: One of these things is NOT like

Q110: A project manager that uses milestones as

Q112: Use the earned value table for Project

Q114: Use the earned value table for Project

Q115: Earned value management is also known as:<br>A)the

Q116: Use the data to calculate the schedule

Q117: The budget variance is calculated as:<br>A)earned value

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines