Multiple Choice
Use the data to calculate the schedule performance index for the project for the end of week 20.All amounts are in thousands of dollars.
A) 1.14
B) 0.88
C) 0.94
D) 0.81
Correct Answer:

Verified
Correct Answer:
Verified