Use the Project Described in the Table to Determine the Total

Question 37

Multiple Choice

Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day) to this project. Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day) to this project.   A) 4 hours B) 2 hours C) 8 hours D) 6 hours


A) 4 hours
B) 2 hours
C) 8 hours
D) 6 hours

Correct Answer:

verifed

Verified