A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?
A) Activities A,B,and C
B) Activities B,C,and D
C) Activities C,D,and E
D) Activities D,E,and F
Correct Answer:

Verified