Use the Project Described in the Table to Determine the Total

Question 4

Multiple Choice

Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis. Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.   A) 5 hours B) 10 hours C) 4 hours D) 8 hours


A) 5 hours
B) 10 hours
C) 4 hours
D) 8 hours