Multiple Choice
A resource loading chart displays:
A) the amount of time needed as a function of resource limits.
B) the amount of resources required as a function of time.
C) the amount of time needed as a function of money.
D) the amount of resources needed as a function of money.
Correct Answer:

Verified
Correct Answer:
Verified