Multiple Choice
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?
A) week 4
B) week 5
C) week 6
D) week 7
Correct Answer:

Verified
Correct Answer:
Verified