Use the Information in the Table and Assume That a Worker

Question 24

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?   A) 22 hours B) 88 hours C) 44 hours D) 132 hours


A) 22 hours
B) 88 hours
C) 44 hours
D) 132 hours

Correct Answer:

verifed

Verified