Multiple Choice
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?
A) 22 hours
B) 88 hours
C) 44 hours
D) 132 hours
Correct Answer:

Verified
Correct Answer:
Verified