Multiple Choice
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?
A) 365 hours
B) 335 hours
C) 320 hours
D) 310 hours
Correct Answer:

Verified
Correct Answer:
Verified