Question 17

Multiple Choice

Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?   A) 365 hours B) 335 hours C) 320 hours D) 310 hours


A) 365 hours
B) 335 hours
C) 320 hours
D) 310 hours

Correct Answer:

verifed

Verified