Use the Project Described in the Table to Determine the Total

Question 19

Multiple Choice

Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis. Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project.Assume that the project work is conducted on a 5-day-per-week basis.   A) 40 hours B) 20 hours C) 28 hours D) 36 hours


A) 40 hours
B) 20 hours
C) 28 hours
D) 36 hours