Multiple Choice
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements?
A) day 15
B) day 19
C) day 24
D) day 29
Correct Answer:

Verified
Correct Answer:
Verified