Multiple Choice
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:
A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
Correct Answer:

Verified
Correct Answer:
Verified