Multiple Choice
XYZ project organization has one workstation that is capable of generating the drawings that their clients study before accepting XYZ's bid.XYZ is currently in the midst of three proposal projects and knows exactly when it will need to use the workstation.All other work to be done,both before and after the workstation is used,is scheduled such that it flows to the workstation and keeps it busy.Resources used after this step are less critical;so while the subsequent work and resources are important,they aren't viewed with the same reverence as the workstation.This is an example of:
A) identifying a constraint.
B) elevating a constraint.
C) subordinating a system.
D) exploiting a constraint.
Correct Answer:

Verified
Correct Answer:
Verified
Q76: Your next project consists of 5 consecutive
Q95: What is the difference between the critical
Q107: Create an example and explain how it
Q108: Which of the following statements about CCPM
Q109: The first step in TOC methodology is
Q110: A worker is assigned three tasks,A,B,and C,each
Q112: Which of the following is an example
Q114: What are the recommendations for applying the
Q115: A project is represented by the activity
Q117: CCPM advocates putting off non-critical activities as