Multiple Choice
The best thing a project manager can do when noticing common cause variation in a project's monthly budget summary is to:
A) call another meeting and brainstorm causes for the variance.
B) call the workers responsible for the variance into the office and dismiss them immediately.
C) do nothing.
D) call the suppliers responsible for the increased cost and negotiate lower material costs.
Correct Answer:

Verified
Correct Answer:
Verified