Multiple Choice
If a project activity experiences positive variation:
A) the following activity must be started later than anticipated.
B) the preceding activity must be started later than anticipated.
C) the following activity can be started earlier than anticipated.
D) the preceding activity can be started earlier than anticipated.
Correct Answer:

Verified
Correct Answer:
Verified