Multiple Choice
Your next project consists of 8 consecutive 8-day activities,each estimated by a different worker in your organization.Your organizational culture dictates that you add your own safety margin of 3 days into your estimates.Unbeknownst to you,the project manager has recently converted to a critical chain project management view.The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place.What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule?
A) 12 days
B) 6 days
C) 18 days
D) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q45: A project is represented by the
Q46: A project that consists of six
Q47: Which of these numerical (quantity)comparisons is CORRECT?<br>A)Scrum
Q48: Which of the following statements about CCPM
Q49: A project consists of four consecutive
Q51: Your next project consists of 10 consecutive
Q52: Compose a haiku using three or more
Q53: A system-wide constraint is called a:<br>A)Rope.<br>B)Resource.<br>C)Drum.<br>D)Chain.
Q55: What are the key elements of extreme
Q74: The one element that Agile shares with