Multiple Choice
The most common method for shortening activity durations involves the decision to:
A) eliminate bureaucracy.
B) alter the technology used in the activity.
C) assign more senior personnel to the activity.
D) increase project resources.
Correct Answer:

Verified
Correct Answer:
Verified