Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 13

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible?   A) 60 weeks B) 57 weeks C) 53 weeks D) 50 weeks


A) 60 weeks
B) 57 weeks
C) 53 weeks
D) 50 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions