Solved

It Costs $75 Per Day for Each Day That a Construction

Question 104

Multiple Choice

It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.   A) $1,800 B) $1,770 C) $1,700 D) $1,630


A) $1,800
B) $1,770
C) $1,700
D) $1,630

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge