menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks
  5. Question
    A Project Has the Activity Duration and Cost Information Indicated
Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 103

Question 103

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?   A) $222,667 B) $243,675 C) $258,333 D) $272,500


A) $222,667
B) $243,675
C) $258,333
D) $272,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q75: Most activity estimations using PERT methods lead

Q81: How might a project manager alter a

Q90: Most project management software employs AOA diagramming.

Q98: Start-to-start lags are becoming increasingly used as

Q99: A project has the activity duration and

Q104: It costs $75 per day for each

Q105: Use the Gantt chart and activity list

Q106: Use the Gantt chart and activity list

Q107: Use the Gantt chart and the activity

Q108: The heir to the throne was due

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines