Multiple Choice
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?
A) $234,000
B) $255,600
C) $248,333
D) $252,000