Solved

A Project Has the Activity Duration and Cost Information Indicated

Question 79

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?   A) $234,000 B) $255,600 C) $248,333 D) $252,000


A) $234,000
B) $255,600
C) $248,333
D) $252,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions